Report for August 2012

Report Date
August 2012

Report for August 2012

Submitted by Stevie Conlon

 

Achievements in Last Period

After the deployment of the POLO database upgrade, the MediaBank began to exhibit response times issues. The development team coded a solution which was rolled out on the 13th of August to resolve an indexing problem on Media bank content. The code was rolled out and the re-indexing was run but this did not resolve the issue. A further workround was added to address the particular area of slowness and this was rolled out on the 25th of August. This was successful in alleviating the response time issue with the user base. 

 

Issues

The project has gone over buget due to the additional efforts to resolve the Media Bank issues.

 

Next Steps

The next steps will be to collate the views from the closure reports to discuss whether we can live with the application in its current state and accept there may be some risk with response times in the future or to decide to initiate another project

Milestones

 

13-Aug-2012

Go Live with fix for Media Bank Performance

23-Aug-2012

Deploy Media Bank tuning fix to LIVE

06-Sep-2012

DSOR - Review Media Bank deployment and Upgrade

13-Sep-2012

Project Closure

 

.

Project Status
RAG Status
Time
RED
Cost
RED
Scope
RED
Overall
RED
Change Status
Activity
Approved budget
41.5 days
Activity this month
19.9 days
Activity this year
19.9 days
Activity to date
54.8 days
Estimate to complete current year
2.5 days
Estimate to complete future years
2.5 days

Project Info

Project
POLO Database Upgrade
Code
ITS098
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Stephen Conlon
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
21-May-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Sep-2012