Completion Report

Project Summary:

The deliverables achieved were the DEV, TEST and LIVE instances of EUPS database applications in use moved to the APPS database and upgraded to the Oracle version 11g. Applications using the database were assessed for the move.

1. MyEd Channels (EPS)

Student Personal Details

Student Courses

Student Program of Study

and

 2. EVE student voting

 

 

Analysis of Resource Usage:

Staff Usage Estimate: 26 days

Staff Usage Actual: 27.5 days

Staff Usage Variance: 6%

Other Resource Estimate: 0 days

Other Resource Actual: 0 days

Other Resource Variance: 0%

Explanation for variance:

Additional analysis and meetings to determine the approach and scope added additional time. As did the discussion around which schemas were actually to be migrated.

Two applicatons , U@Ed and SCWEIMS did not have their schemas moved as they were no longer required.

 

Key Learning Points:

A central dictionary/repositary of applications , their usage and ownership would have been advantageous to the project in determining the initial scope of applications for migration. For example, the planned retiral of U@ED.

 

 

Outstanding issues:

No outstanding issues.

Project Info

Project
EUPS Database Upgrade
Code
ITS099
Programme
Z. ISG - Web Integration (WIT) (Closed)
Project Manager
Stephen Conlon
Project Sponsor
Martin Morrey
Current Stage
Close
Status
Closed
Start Date
01-May-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Aug-2013

Documentation

Close