Organisation
Work/Task Breakdown
Initiate
Produce Project Brief - Project Team, Project Sponsor
Plan
Identify End users for the EUPS schemas– Project Services, Applications Management
Agree testing with End users - Project Services
Produce project plan - Project Services
Do It
Investigate Feeds and connections - ~Development Technology.
Upgrade DEV database – Development Technology
Initial testing - Development Technology
Upgrade TEST database – Development Technology
Check It
Carry out UAT – Service Management, SACS
Respond to any UAT issues: Development Technology
Test Feeds when the EUPS TEST schemas are unavailable to ascertain if there are any issues for the live upgrade.
Deployment checklist - Technology Management.
Raise Alert for LIVE deployment - Project Services
Release
Upgrade APS LIVE with the new schemas - Development technology
Production Hand-over - Technology Management, Development Technology
Close
Project Sponsor, Project management, Technology Management, Applications Management, Development Technology
Resources Skills and Cost
The project is estimated to require 27 days effort by IS Applications. The estimates include the effort spent previously on this project earlier in the year.
The project will require effort from Project Services, 9 days for scoping, planning, brief production and testing support.
Development Technology. 17 days for schema moves and Testing Support rework
Technology Management. 1 day
The Project Sponsor and users will undertake UAT.