Report for June 2013
- Report Date
- June 2013
- Achievements in Last Period
Testing has progressed in TEST APPS environment with both SACs and Service Management.
SACS users issues to use Test MyEd users were resolved. Identity switch method used for this testing.
Issues found in testing U@ED mitigated by the fact the application will now be closed of and no longer used.
- Issues
Service owner to determine if BO users will need re-added to the new APPs database schemas. PM to follow up.
- Next Steps
Sign Off testing (ASOR)
Upgrade LIVE environment.
DSOR and Closure.
15-Jul-2013 | ASOR |
17-Jul-2013 | Deploy to LIVE - Upgrade LIVE Instance of APPS with EUPS Schemas |
22-Jul-2013 | DSOR |
26-Jul-2013 | Project Closure |
- Approved budget
- 27.0 days
- Activity this month
- 1.0 day
- Activity this year
- 20.0 days
- Activity to date
- 26.0 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days