Report for June 2013

Report Date
June 2013
 
  • Achievements in Last Period

Testing has progressed in TEST APPS environment  with both SACs and Service Management.

SACS users issues to use Test MyEd users were resolved. Identity switch method used for this testing.

Issues found in testing U@ED mitigated by the fact the application will now be closed of and no longer used.

  • Issues

Service owner to determine if BO users will need re-added to the new APPs database schemas. PM to follow up.

  • Next Steps

Sign Off testing (ASOR)

Upgrade LIVE environment.

DSOR and Closure.

15-Jul-2013ASOR
17-Jul-2013Deploy to LIVE - Upgrade LIVE Instance of APPS with EUPS Schemas
22-Jul-2013DSOR
26-Jul-2013Project Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
27.0 days
Activity this month
1.0 day
Activity this year
20.0 days
Activity to date
26.0 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EUPS Database Upgrade
Code
ITS099
Programme
Z. ISG - Web Integration (WIT) (Closed)
Project Manager
Stephen Conlon
Project Sponsor
Martin Morrey
Current Stage
Close
Status
Closed
Start Date
01-May-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Aug-2013