Report for May 2013
- Report Date
- May 2013
- Achievements in Last Period
Testing has progressed in TEST APPS environment with both SACs and Service Management.
- Issues
Some BO users will need re-pointed in TEST. App Management to progress.
SACS users unable to use Test MyEd users. Identity switch method used for this to allow testing.
- Next Steps
Sign Off testing (ASOR)
Upgrade LIVE environment.
DSOR and Closure
Target date | Title |
---|---|
12-Jun-2013 | ASOR |
13-Jun-2013 | Deploy to LIVE - Upgrade LIVE Instance of APPS with EUPS Schemas |
18-Jun-2013 | DSOR |
21-Jun-2013 | Project Closure |
- Approved budget
- 27.0 days
- Activity this month
- 0.5 days
- Activity this year
- 20.0 days
- Activity to date
- 25.4 days
- Estimate to complete current year
- 1.6 days
- Estimate to complete future years
- 0.0 days