To migrate the existing databases from the current infrastructure to the new Dell Compellent based SAN infrastructure

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2013 BLUE 54.0 days 49.7 days 0.0

Project Info

Project
SAN Migration
Code
ITS101
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
Karen Stirling
Project Sponsor
David Smyth
Current Stage
Close
Status
Closed
Start Date
03-Jan-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Nov-2013
Category
Compliance

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.