Provide updates to core infrastructure elements. For 13/14 the key items identified are as follows:

 

1.       Migration of central databases to new infrastructure – APPSLIVE and NEWSLIVE. Address the retiral of  MISLIVE and UCDLIVE.

The procedures and experience gained through the project to Implement the new Database tier (ITS100) will be utilised to migrate the stated databases

There is the further requirement to  determine the requirement to migrate the central databases MISLIVE  and UCDLIVE.

2.       Provide a list of applications that require upgrading to cosign version to v3

 

 

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2014 BLUE 194.0 days 200.0 days 0.0

Project Info

Project
Core Technology Updates
Code
ITS103
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
Morna Findlay
Project Sponsor
David Smyth
Current Stage
Close
Status
Closed
Start Date
12-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2014
Programme Priority
1
Overall Priority
Higher
Category
Compliance