LMP - IDM Integration - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2015 BLUE 67.0 days 65.4 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Tuesday, 20 January 2015
Close Date
Friday, 4 September 2015
Project information
Project Code
LMP004
Programme
Z. ISG - Library Management Platform (LMP) (closed August 2017)
Session
15/16
14/15
Organisational Unit
Library and University Collections
Project Category
Discretionary
Programme Priority
3
Overall Priority
Normal