June Report

Report Date
June 2015

Achievements in Last Period

  • Technical Architecture Design Document signed off by Heather Larnach, Technology Management
  • IDM load tested and data confirmed by Library
  • UAT signed off verbally by Library team for IDM feed
  • UAT signed off by Library team for MYED Changes
  • MyEd Changes have been approved by Martin Morrey for deployment on 30th June
  • Implementation plan reviewed and rollout steps
  • Preparation for go-live / deploy to live

 

Issues

  • Handover to Production to be scheduled week commencing 29th June as resource on annual leave

 

Next Steps

  • Deployment review
  • Closure of sub projects

 

The project status is GREEN

29-Jun-2015

Delivery

10-Jul-2015

Deployment Review

31-Jul-2015

Closure

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
67.0 days
Activity this month
9.2 days
Activity this year
60.0 days
Activity to date
60.0 days
Estimate to complete current year
1.2 days
Estimate to complete future years
0.0 days

Project Info

Project
LMP - IDM Integration
Code
LMP004
Programme
Z. ISG - Library Management Platform (LMP) (closed August 2017)
Project Manager
Karen Stirling
Project Sponsor
Bryan MacGregor
Current Stage
Close
Status
Closed
Start Date
20-Jan-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Sep-2015
Programme Priority
3
Overall Priority
Normal
Category