June Report
- Report Date
- June 2015
Achievements in Last Period
- Technical Architecture Design Document signed off by Heather Larnach, Technology Management
- IDM load tested and data confirmed by Library
- UAT signed off verbally by Library team for IDM feed
- UAT signed off by Library team for MYED Changes
- MyEd Changes have been approved by Martin Morrey for deployment on 30th June
- Implementation plan reviewed and rollout steps
- Preparation for go-live / deploy to live
Issues
- Handover to Production to be scheduled week commencing 29th June as resource on annual leave
Next Steps
- Deployment review
- Closure of sub projects
The project status is GREEN
29-Jun-2015 | |
10-Jul-2015 | |
31-Jul-2015 |
- Approved budget
- 67.0 days
- Activity this month
- 9.2 days
- Activity this year
- 60.0 days
- Activity to date
- 60.0 days
- Estimate to complete current year
- 1.2 days
- Estimate to complete future years
- 0.0 days