August Report
- Report Date
- August 2015
Achievements in last Period
- UNIDESK Call raised by Library around staff end dates / purge date resulted in fix to code for expiry date and also fixed was default email addresses. Deployed to live on 25th Ausgust and confirmed working by Library and Helpdesk teams.
- Project closure requested to allow completion report to be submitted to IS Apps Internal approval
- Estimates for change based feed and split of report for Student and Staff has been provided and will be taken forward in LMP006
- Issues
Deployment of fixes now resolved but has delayed project closure, chasing for final sign offs for Project Closure report and submit to IS Apps for approval
Next Steps
- Project Closure approval
- Approved budget
- 67.0 days
- Activity this month
- 1.3 days
- Activity this year
- 1.3 days
- Activity to date
- 65.4 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days