November 2024
- Report Date
- November 2024
Last Month.
-
Met with the project development team to discuss the project's next steps, the team is still experiencing time constraints as a result of other priorities.
-
Discussed with the project stakeholders and agreed to pause (suspend) the project until the development team is available to proceed to the next steps.
Issues.
- This project has experienced resource constraints due to other prioritised projects by the development team within LTW.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days