Closure Report

 

Project Summary

This project was to assist with the re-opening of the Main Library building in line with the Governments COVID-19 guidelines. This work was already well under way before Project Services were involved which meant the project was mainly a co-ordination piece of the work streams. 

 

Deliverable 1.1 - RIsk Assessments for all areas of the building complete : DELIVERED

Deliverable 1.2 - All relevant signage in place including one way systems and social distancing markers : DELIVERED

Deliverable 1.3 - Cleaning stations in place through out the building : DELIVERED

Deliverable 1.4 - Queue Management System in place to control numbers of people within the building : DELIVERED

Deliverable 1.5 - Defined Break out spaces for staff : DELIVERED

Analysis of Resource Usage:

Staff Usage Estimate: 10 days

Staff Usage Actual: 5.6 days

 

Explanation for Variance

There was a possibility this project would pick up the re-opening of some of the other smaller libraries but as they we re being used to provide study spaces this was covered under the study spaces project, so the full time allocation was not required. 

Outcome

The project delivered on its main objectives required to get the Library re-opened in a safe manner on time. 

Outstanding Issues

The main outstanding issue was finishing the study spaces booking app. As this was not able to be launched in time for the reopening of the library a manual process was put in to place to manage queues and co-ordinate study space bookings. The launch of the app is covered under the Study Spaces project and when it is launched it will simplify the queue management and improve the experience for people attending the library . 

 

Project Info

Project
Main Library Reopening
Code
LUC032
Programme
Library and Collections – Return to Campus (LUCRTC)
Management Office
ISG PMO
Project Manager
Frankie Quinn
Project Sponsor
Jeremy Upton
Current Stage
Close
Status
Closed
Start Date
31-Aug-2020
Planning Date
04-Sep-2020
Delivery Date
14-Sep-2020
Close Date
18-Sep-2020
Overall Priority
Normal

Documentation

Close