Report for September 2020

Report Date
September 2020

Achievements this period

  • Project Brief
  • Project Plan
  • Deliver Project Outcomes

Issues

Project closure is slightly delayed as awaiting confirmation from the Sponsor they are happy for it to be closed

 

Achievements Next Period

  • Project Closure

 

Milestones

 

Stage Milestone Due Date
Initiate Project Brief 02-Sep-2020
Plan Project Plan Complete 04-Sep-2020
Deliver Deliver Project Outcomes 14-Sep-2020
Close Project Closed 18-Sep-2020
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
10.0 days
Activity this month
3.9 days
Activity this year
5.5 days
Activity to date
5.5 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Main Library Reopening
Code
LUC032
Programme
Library and Collections – Return to Campus (LUCRTC)
Management Office
ISG PMO
Project Manager
Frankie Quinn
Project Sponsor
Jeremy Upton
Current Stage
Close
Status
Closed
Start Date
31-Aug-2020
Planning Date
04-Sep-2020
Delivery Date
14-Sep-2020
Close Date
18-Sep-2020
Overall Priority
Normal