September 2022
- Report Date
- September 2022
Cataloguing progress:
R(D)SVS - cataloguing is ongoing and approaching completing cataloguing of the staff records. A target has been made to complete the cataloguing by the end of 2022 in time for the bicentenary in 2023
OneKind - cataloguing can begin in September. The archival structure has been approved and I can begin cataloguing the collection. Decisions are still to be made as to deciding what boxes, folders etc. need to be ordered to rehouse the collection.
RZSS - There is a lot more material than previously anticipated so it is taking a while to go through all the material they have there.
Conservation progress:
Mhairi in post as Project Conservator as of 1st August 2022. She has completed a conservation survey of the OneKind material and has begun conservation work on the larger volumes in the R(D)SVS archive.
Other:
The twitter and blog are continuing to be contributed to. There are plans in place from September to contribute to the Craigmillar learning programme on the topic of zoology.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days