Report for November 2024

Report Date
November 2024

 

Achievements in Last Period

LUC065-151 Aura accessibility test

Issues and Risks

  • Stakeholders are looking for  assurances that Orchid integration will be delivered as part of upgrade
  • Industrial action impacting delivery.
  • Resources over deployed across department resulting in delays.
  • Cambridge have informed of service degradation with new Dspace 7 instances, will measure on vanilla installs and revert

Next Steps

LUC065-103 QMU extra functionality (ref report)
LUC065-148 AURA Pure connector testing
LUC065-150 Exam Papers Fix
LUC065-156 Download Zip file function for Datashare
LUC065-157 HW Shib
LUC065-158 HW theses collection to Dspace6
LUC065-160 Datashare download puppet changes

 

Future Milestones

  • Continue with development tasks throughout industrial action  
Milestone Date
Start 01-Oct-2022
Plan 01-Oct-2022
Deliver  18-Dec-2024
Close 17-Jan-2025

 

Project Sponsor Commentary / Approval

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
Yes
Escalated to
Ianthe Sutherland
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
DSpace 7 Upgrades
Code
LUC065
Programme
Library & Collections - Digital Library BAU (LUCDL)
Management Office
ISG PMO
Project Manager
Ianthe Sutherland
Project Sponsor
Ianthe Sutherland
Current Stage
Execute
Status
In Progress
Start Date
01-Sep-2022
Planning Date
01-Nov-2022
Delivery Date
18-Dec-2024
Close Date
17-Jan-2025
Category
Compliance

Documentation