Report for November 2024
- Report Date
- November 2024
Achievements in Last Period
LUC065-151 | Aura accessibility test |
Issues and Risks
- Stakeholders are looking for assurances that Orchid integration will be delivered as part of upgrade
- Industrial action impacting delivery.
- Resources over deployed across department resulting in delays.
- Cambridge have informed of service degradation with new Dspace 7 instances, will measure on vanilla installs and revert
Next Steps
LUC065-103 | QMU extra functionality (ref report) |
LUC065-148 | AURA Pure connector testing |
LUC065-150 | Exam Papers Fix |
LUC065-156 | Download Zip file function for Datashare |
LUC065-157 | HW Shib |
LUC065-158 | HW theses collection to Dspace6 |
LUC065-160 | Datashare download puppet changes |
Future Milestones
- Continue with development tasks throughout industrial action
Milestone | Date |
Start | 01-Oct-2022 |
Plan | 01-Oct-2022 |
Deliver | 18-Dec-2024 |
Close | 17-Jan-2025 |
Project Sponsor Commentary / Approval
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days