Report for September 2012

Report Date
September 2012

Achievements in Last Period

  • Shibboleth implemented on LIVE 07/09/12
  • DNS configured 14/09/12, propogated and site live at new address 17/09/12
  • Design of public facing site completed 27/09/12.

 

Issues

  • Customer requested changes to functionality of deployed modules as a result of UAT. We are negotiating with them for additional funding. Project is amber because of this.

 

Next Steps

  • Deploy agreed public-facing site by 01/10/12
  • Final sign off by IDCore 05/10/12
  • Project closure 19/10/12

 

Target dateTitle
01-Oct-2012Deploy Public facing Site
05-Oct-2012IDCore final sign 0ff
19-Oct-2012Project closure
 IS Apps Excluding SM (including SM prior to 6/8/12)IS Apps Including SM 
Approved Budget  30.0
Activity this month1.74.6 
Activity this year1.710.4 
Activity to date25.310.4 
Effort to Complete0.30.5 
Total effort expected for project25.510.936.4

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
IDCore Drupal Web Project
Code
MED001
Programme
Z. Media (closed 2012/13)
Project Manager
Chris McKay
Project Sponsor
David Ingram
Current Stage
Close
Status
Closed
Start Date
07-Mar-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Nov-2012
Programme Priority
1
Overall Priority
Normal
Category
Discretionary