Report for September 2012
- Report Date
- September 2012
Achievements in Last Period
- Shibboleth implemented on LIVE 07/09/12
- DNS configured 14/09/12, propogated and site live at new address 17/09/12
- Design of public facing site completed 27/09/12.
Issues
- Customer requested changes to functionality of deployed modules as a result of UAT. We are negotiating with them for additional funding. Project is amber because of this.
Next Steps
- Deploy agreed public-facing site by 01/10/12
- Final sign off by IDCore 05/10/12
- Project closure 19/10/12
Target date | Title |
---|---|
01-Oct-2012 | Deploy Public facing Site |
05-Oct-2012 | IDCore final sign 0ff |
19-Oct-2012 | Project closure |
IS Apps Excluding SM (including SM prior to 6/8/12) | IS Apps Including SM | ||
Approved Budget | 30.0 | ||
Activity this month | 1.7 | 4.6 | |
Activity this year | 1.7 | 10.4 | |
Activity to date | 25.3 | 10.4 | |
Effort to Complete | 0.3 | 0.5 | |
Total effort expected for project | 25.5 | 10.9 | 36.4 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days