October 2019

Report Date
October 2019
Issues & Changes
  • The Data Lab has advised that the MOOC will not run.
Next Steps
  • Close project.
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
RAG Commentary
Project to close.
Change Status
Overall
Significant
Has formal escalation taken place?
No
Change Commentary
Project to close.
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Driving Value from Data and A.I.
Code
MOOC028
Programme
MOOC Development Projects (In Delivery)
Management Office
ISG PMO
Project Manager
Colette Maxwell
Project Sponsor
Melissa Highton
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-Sep-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
24-Oct-2019