Organisation

Work/Task Breakdown, Resources Skills and Cost

Project Manager - 1 day

Business Analysis

8 days estimate

1. Meet with Caroline Brett - w/c 1/6 2. Create first draft of the IGT requirements (highlight initial thoughts on whether there are standard/generic or project specific/non generic documents available) - by 5/6 3. Match standard documents to IGT requirements and create links in the spreadsheet - by 12/6 4. Meet with the group for initial review - w/c 15/6 5. Amendments to the standard documents and updates following the initial review - by 19/6 6. Produce IT documentation checklist - by 25/6  

8 days estimate a. Initial draft (4 days) b. Meet with group for review (1 day) c. Update and store templates and create links (3 days)

 

 

 

 

Project Info

Project
Template research administration documentation set
Code
MVM007
Programme
MVM Research (MVMRES)
Project Manager
Maurice Franceschi
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
05-Jun-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jul-2016
Programme Priority
3
Overall Priority
Normal
Category
Discretionary