June 2016

Report Date
June 2016

Achievements in Last Period

 

  • draft SLSP in place - done
  • sign-off of documentss from stakeholders - done
  • sign-off from Myke - done
  • feedback and sign-off from pilot group - done
  • ownership of document post-project agreed - assumed it wil be Paul

Issues

  • no medium or high risks

Next Steps

  • handover to owner
  • closure  

Milestones

30-Jun-2016Post-Project Document Support in Place
15-Jul-2016Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
30.0 days
Activity this month
5.0 days
Activity this year
25.0 days
Activity to date
35.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Template research administration documentation set
Code
MVM007
Programme
MVM Research (MVMRES)
Project Manager
Maurice Franceschi
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
05-Jun-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jul-2016
Programme Priority
3
Overall Priority
Normal
Category
Discretionary