Current project status

Report Date RAG Budget Effort Completed Effort to complete
March 2017 BLUE 175.0 days 179.0 days 1.0
Content
Status
Closed
Current Stage
Close
Start Date
Friday, 28 August 2015
Close Date
Friday, 17 March 2017
Project information
Project Code
MVM009
Programme
MVM Business Administration (MVMBUS)
Session
16/17
15/16
Organisational Unit
College of Medicine & Veterinary Medicine
Project Management Office (if relevant)
ISG PMO
Project Category
Discretionary
Overall Priority
Higher