January 2017

Report Date
January 2017

Achievements in Last Period

  • Contract negotiations have continued throughout the month. 
  • Project Board meeting took place 19/01/17; members were updated on progress with the contract; some actions were agreed to carry some issues into the implementation project (MVM509).
  • Procurement and legal expected work to be complete on the contract w/c 30/01/17 for approval by David Argyle and Gavin McLachlan.

 

Issues

  • No major issues; contract negotiations still not complete; PM and Procurement Manager attempting to expedite the completion.

 

Next Steps

  • Complete contract negotiations and get contract signed off by all parties.
  • Agree (procurement) project closure.

The project current status is AMBER due to delays completing contract negotiations.

 

Milestones

(NB outstanding milestones remain subject to change due to ongoing contract negotiations)

13-Feb-2017 Contract Signed
20-Feb-2017 Closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Amber due to delays in finalising contract
Change Status
Activity
Approved budget
175.0 days
Activity this month
6.0 days
Activity this year
47.0 days
Activity to date
176.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Tristan Replacement - Procurement
Code
MVM009
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
David Argyle
Current Stage
Close
Status
Closed
Start Date
28-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Mar-2017
Overall Priority
Higher
Category
Discretionary

Documentation