March 2016

Report Date
March 2016

Achievements in Last Period

  • resource decision - not decided
  • brief - in development
  • estimaton and planning - summer 2016 unlikely - estimation sent out to sponsor and keystakeholders
  • identify quick wins - achieved

Issues and Risks

  • need decision on resource for the project
  • need a decision on resource for support  
  • Next Steps
  • resource decisions
  • decide if we need ot wait for Windows 10 to be in place
  • complete brief if project to proceed

Milestones

 

08-Apr-2016End of Planning
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Integration and adoption of ISFM
Code
MVM024
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Muriel Mewissen
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
28-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Jan-2017