Report for June 2017

Report Date
June 2017

Achievements

  • Purchase order agreed, created and delivered to FRY-IT to support Legal review of T&C

Issues

  • Both of the remaining Milestones were moved out by approx. a month - agreed as new target dates, no dates have been agreed with Fry-IT to complete, though some pressure has been applied
  • No new risks emerged-Two risks remain around the contract and sign off, status viewable from the project link: https://www.projects.ed.ac.uk/unpublished/project/mvm107/risks

Next Steps

  • Procurement and Legal will now manage the T&C's from FRY-IT through to a successful contract
  • Create the closure report
  • This project will close

 

Milestones

31-Jul-2017 30-Jun-2017 Deployment complete - Award Contract Milestone Deliver No

view

21-Aug-2017 28-Jul-2017 Project Completion Milestone Close No

view

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
80.0 days
Activity this month
0.7 days
Activity this year
84.8 days
Activity to date
84.8 days
Estimate to complete current year
0.6 days
Estimate to complete future years
0.0 days

Project Info

Project
Procurement of an online application to support assessment and feedback for MBChB
Code
MVM107
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Paul De'Ath
Project Sponsor
David Kluth
Current Stage
Close
Status
Closed
Start Date
24-Oct-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Aug-2017
Programme Priority
1
Overall Priority
Highest
Category
Discretionary

Documentation