Report for June 2017
- Report Date
- June 2017
Achievements
- Purchase order agreed, created and delivered to FRY-IT to support Legal review of T&C
Issues
- Both of the remaining Milestones were moved out by approx. a month - agreed as new target dates, no dates have been agreed with Fry-IT to complete, though some pressure has been applied
- No new risks emerged-Two risks remain around the contract and sign off, status viewable from the project link: https://www.projects.ed.ac.uk/unpublished/project/mvm107/risks
-
Next Steps
- Procurement and Legal will now manage the T&C's from FRY-IT through to a successful contract
- Create the closure report
- This project will close
Milestones
-
31-Jul-2017 30-Jun-2017 Deployment complete - Award Contract Milestone Deliver No 21-Aug-2017 28-Jul-2017 Project Completion Milestone Close No
- Approved budget
- 80.0 days
- Activity this month
- 0.7 days
- Activity this year
- 84.8 days
- Activity to date
- 84.8 days
- Estimate to complete current year
- 0.6 days
- Estimate to complete future years
- 0.0 days