Report for July 2017
- Report Date
- July 2017
Achievements
- Meeting held with Legal representation from UoE and Fry-IT to review the T&C and all associated comments and responses
- Both teams seeking to complete the T&C's in early August
- Contract signatories have been agreed on both sides
- Business sponsor has agreed to a budget increase to cover the PM work in completing the sign off of the contract and then closing the project down
Issues
- IS WIS have approved the initial final two milestone date moves (see below) which sees the project just creeping into the next financial year
- Budget increased from 80 days to 93 days - as a consequence of the time taken by both parties requiring several interventions from the PM
- No new risks emerged-Two risks remain around the contract and sign off, status viewable from the project link: https://www.projects.ed.ac.uk/unpublished/project/mvm107/risks
-
Next Steps
- Procurement and Legal will now manage the T&C's from FRY-IT through to a successful contract
- Create the closure report
- This project will be closed, with a review at IS WIS
-
Milestones
-
31-Jul-2017 Deployment complete - Award Contract Milestone Deliver 21-Aug-2017 Project Completion Milestone Close
- Approved budget
- 93.0 days
- Activity this month
- 7.5 days
- Activity this year
- 92.5 days
- Activity to date
- 92.5 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 2.0 days