Impact
Priority and Funding
This is a priority 2 project.
Although the priority for this project in the MVMLAT programme and in the MVM portfolio is 1.
It is sponsor and discretionary funded.
Impact and Dependencies
This project has a dependency upon the contract negotiations completing on time, by mid May 2017 - MVM107 - Risk raised.
This project is expected to have a dependency with MVM119, which will generate and migrate data into the application. Details still to be worked through - Risk raised.
Dependency risks:-
https://www.projects.ed.ac.uk/unpublished/project/mvm118/risks/1 - MVM107
https://www.projects.ed.ac.uk/unpublished/project/mvm118/risks/4 - MVM119
The completion of this programme (MVM107, MVM118 and MVM119) will have an impact upon the use and support requirements for OSCA and OSCA+. Decommission is now within the scope of this programme, it is highly likely that OSCA+ may become an archive system, no longer used in Production, but required in the short term as a backup, before decommission completes.
Project Risks
(as of Thursday May 18, 2017)
Ref | Title | Impact | Probability | Risk | Status | Risk Owner | Date of Last Review | |
---|---|---|---|---|---|---|---|---|
1 | MVM107 - Dependency on contract being signed off | Low | Medium | GREEN | Open | Paul De'Ath | 05-May-2017 | |
2 | Third party code - not standard, IS mitigation | Low | Medium | GREEN | Open | Paul De'Ath | 05-May-2017 | |
3 | Timescales and key resource availability | Medium | Low | GREEN | Open | Paul De'Ath | ||
4 | Inter dependency with MVM119 | Low | Low | GREEN | Open | Paul De'Ath | 16-May-2017 | |
5 | Euclid requirements | Low | Low | GREEN | Open | Paul De'Ath | ||
6 | OSCA and OSCA+ decommission | Low | Low | GREEN | Open | Paul De'Ath |