Report for May 2018

Report Date
May 2018
Achievements
  • Deployed new release to Production
  • Preparing for the project to be closed

Issues

  • No new risks identified

Next Steps

  • Close project following the initiation of the follow-on OSCE project (MVM129)

 

Milestones

  • N/A
 

 

 

Project Status
RAG Status
Time
GREEN
Cost
RED
Scope
GREEN
Overall
RED
RAG Commentary
Issue - The budget has been exceeded. Business Sponsor has agreed. The Project will be closed next week, no requirement for SMT involvement.
Change Status
Activity
Approved budget
90.0 days
Activity this month
8.5 days
Activity this year
93.9 days
Activity to date
114.6 days
Estimate to complete current year
5.3 days
Estimate to complete future years
0.0 days

Project Info

Project
Deployment of FRY-IT Practique for MBChB
Code
MVM118
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Paul De'Ath
Project Sponsor
Sheila Fraser
Current Stage
Close
Status
Closed
Start Date
01-May-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Jun-2018
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation