Impact

Priority and Funding

This is a priority 2 project.

Although the priority for this project in the MVMLAT programme and in the MVM portfolio is 1.

It is sponsor and discretionary funded.

 

Impact and Dependencies

This project has a dependency upon the contract negotiations completing on time, by mid May 2017 - MVM107 - Risk raised.

This project also has a dependency with MVM118, which will actually deploy the new application. Details still to be worked through - Risk raised.

Dependency risks:-

The completion of this programme (MVM107, MVM118 and MVM119) will have an impact upon the use and support requirements for OSCA and OSCA+. Although decommission is not within the scope of this project, it is in scope for the programme and will be contained within MVM118.

 

Project Risks

(as of Wednesday May 17, 2017)

Ref Title Impact Probability Risk Status Risk Owner Date of Last Review  
1 MVM107 - Dependency on contract being signed off Medium Medium AMBER Open Paul De'Ath 12-May-2017

view

2 Timescales and key resource availability Low Medium GREEN Open Paul De'Ath  

view

3 Inter dependency with MVM118 Low Low GREEN Open Paul De'Ath 16-May-2017

view

4 OSCA and OSCA+ data validation Low Low GREEN Open Paul De'Ath  

view

5 Academic agreement to tagging hierarchy Low Low GREEN Open Paul De'Ath  

view

 

Project Info

Project
Data Creation and Migration into Practique for MBChB
Code
MVM119
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Paul De'Ath
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
01-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Nov-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation

Plan