Report for April 2017

Report Date
April 2017
Achievements
  • The Project initiation was approved at the IS WIS on April 14
  • FRY-IT have supplied the data import template for the first exam from OSCA+ that has been identified to be migrated
  • LTW development confirm they will commence the initial extract in the first week of May

Issues

Next Steps

  • LTW Dev will produce the first data extract according to the suppliers, FRY-IT, template
  • PM meeting with FRY-IT on the week commencing May 1st to run through the high level plan - will include MVM118 (which will be initiated in the first week of May)

Milestones

13-Apr-2017 No date available MVM107 dependency - procurement recommendation report approved Initiate Yes

 

19-May-2017 No date available Present Project Brief to IS WIS Plan No

 

30-Jun-2017 No date available Mock Exam content ready to run Execute No

 

29-Sep-2017 No date available Year 6 Formative Exam ready Execute No

 

30-Nov-2017 No date available Year 5 Summative Exam ready Execute No

 

21-Dec-2017 No date available Recommendation report created Execute No

 

31-Jan-2018 No date available Close report created Close No

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
20.0 days
Activity this month
2.0 days
Activity this year
2.0 days
Activity to date
2.0 days
Estimate to complete current year
8.0 days
Estimate to complete future years
10.0 days

Project Info

Project
Data Creation and Migration into Practique for MBChB
Code
MVM119
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Paul De'Ath
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
01-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Nov-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation