Report for May 2017

Report Date
May 2017
Achievements
  • The Project Brief was approved at the IS WIS on May 26
  • LTW development have created an extract tool that is being used by MBChB in OSCA
  • MBChB staff continue to progress identification of all data content required from OSCA and OSCA+

Issues

Next Steps

  • MBChB will continue to extract all required data from OSCA
  • Depending on contract negotiations with FRY-IT, it is hoped to agree a high level timeline with FRY including agreement on data cleansing approach

Milestones

19-May-2017 No date available End of Planning - Project brief approval Plan Yes

view

02-Jun-2017 No date available OSCA and OSCA+ content identified Execute Yes

view

09-Jun-2017 No date available OSCA and OSCA+ content extract complete Execute No

view

30-Jun-2017 No date available Acceptance - Mock Exam content ready to run Execute No

view

30-Jun-2017 09-Jun-2017 Dependency MVM107 contract with FRY-IT signed Plan No

view

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
As with MVM107 and MVM118, delays to the contract being signed with FRY-IT are likely to have an impact if it doesn't complete this month - though less so with this project currently
Change Status
Activity
Approved budget
30.0 days
Activity this month
9.1 days
Activity this year
11.1 days
Activity to date
11.1 days
Estimate to complete current year
9.1 days
Estimate to complete future years
10.0 days

Project Info

Project
Data Creation and Migration into Practique for MBChB
Code
MVM119
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Paul De'Ath
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
01-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Nov-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation