Report for June 2017

Report Date
June 2017
Achievements
  • MBChB staff have completed their OSCA and OSCA+ extracts
  • The creation of new content has commenced

Issues

Next Steps

  • MBChB and the Project team will commence data cleansing activity removing duplicates from the data extracted
  • Depending on contract negotiations with FRY-IT, it is hoped to agree a high level timeline with FRY-IT, activity list has been discussed (no dates agreed)

Milestones

02-Jun-2017 No date available OSCA and OSCA+ content identified Execute Yes
23-Jun-2017 No date available OSCA and OSCA+ content extract complete Execute No
31-Jul-2017 30-Jun-2017 Dependency MVM107 contract with FRY-IT signed Plan No
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
As with MVM107 and MVM118, delays to the contract being signed with FRY-IT are likely to have an impact if it doesn't complete this month - though less so with this project currently
Change Status
Activity
Approved budget
30.0 days
Activity this month
7.3 days
Activity this year
18.3 days
Activity to date
18.3 days
Estimate to complete current year
1.7 days
Estimate to complete future years
10.0 days

Project Info

Project
Data Creation and Migration into Practique for MBChB
Code
MVM119
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Paul De'Ath
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
01-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Nov-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation