Report for July 2017

Report Date
July 2017
Achievements
  • MVM reviewing OSCA and OSCA+ extracts to remove duplication before Fry-IT formally review and import data (post contract being signed)
  • The creation of new content has continued

Issues

Next Steps

  • Targeting August 21 and 22 for the creation of the UoE environments and formal agreement to activities and dates
  • Depending on contract negotiations with FRY-IT, it is hoped to agree a high level timeline with FRY-IT, activity list has been discussed (no dates agreed)
  • The plan will be re-baselined alongside MVM118, though it is not anticipated that there are any scope changes required.

Milestones

31-Jul-2017 30-Jun-2017 Dependency MVM107 contract with FRY-IT signed
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Issue - As with MVM107 and MVM118, delays to the contract being signed with FRY-IT are likely to have an impact if it doesn't complete this month - though less so with this project currently - targeting early August, which will give the project every opportunity to succeed
Change Status
Activity
Approved budget
30.0 days
Activity this month
1.9 days
Activity this year
20.5 days
Activity to date
20.5 days
Estimate to complete current year
0.0 days
Estimate to complete future years
9.9 days

Project Info

Project
Data Creation and Migration into Practique for MBChB
Code
MVM119
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Paul De'Ath
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
01-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Nov-2017