Report for September 2017
- Report Date
- September 2017
- Achievements
- The first bulk import of content from OSCA/OSCA+ was completed - Year 6 October 19 formative by the project team
- The creation of new content has continued - Year 1 - imported by the project team
- September pilots were executed using new content created for the event
Issues
-
- The supplier, Fry-IT have experienced technical challenges with the bulk import of our OSCA and OSCA+ content - whilst we have an agreed plan to help mitigate, the project team have had to process a number of the critical import files to support Year 6 and Year 1 in particular
- All risks updated and viewable from the project link: https://www.projects.ed.ac.uk/unpublished/project/mvm119/risks
-
Next Steps
- Meeting FRY-IT on Wednesday October 4 to review import issue and agree next steps
- Once bulk import is complete, the proposal is to create a recommendation paper and close this project
-
Milestones
-
Target Date Previous Date Title Stage Complete 27-Sep-2017 22-Sep-2017 Acceptance - Pilot Year 6 Exam content ready to run Deliver Yes
- Approved budget
- 30.0 days
- Activity this month
- 4.7 days
- Activity this year
- 11.0 days
- Activity to date
- 31.5 days
- Estimate to complete current year
- 1.5 days
- Estimate to complete future years
- 0.0 days