Report for October 2017

Report Date
October 2017
Achievements
  • All bulk import of content from OSCA/OSCA+ has completed ok
  • The project team have imported all new content presented to them for all exams in 2017 - Formative and Summative

 

Issues

  • Create a recommendation paper and close this project

 

 

Next Steps

Milestones

Target Datesort descending Previous Date Title Stage Complete
19-Oct-2017 19-Oct-2017 Delivery Complete - Year 6 Formative Exam ready Execute Yes
31-Oct-2017 13-Oct-2017 Implementation - Confirm ready with data - both new and historical from OSCA and OSCA+ Deliver Yes
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
30.0 days
Activity this month
0.0 days
Activity this year
11.0 days
Activity to date
31.5 days
Estimate to complete current year
1.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Creation and Migration into Practique for MBChB
Code
MVM119
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Paul De'Ath
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
01-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Nov-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary