Completion Report

Project Summary:

Analysis of Resource Usage:

Staff Usage Estimate: 1 days

Staff Usage Actual: 1 days

Staff Usage Variance: 0%

Other Resource Estimate: 1 days

Other Resource Actual: 1 days

Other Resource Variance: 0%

Explanation for variance:

.

Key Learning Points:

.

Outstanding issues:

.

Project Info

Project
Windows 10 Deployment to MVM Teaching Spaces
Code
MVM120
Programme
ITI - Windows 10 Upgrade for Managed Desktops (W10)
Management Office
ISG PMO
Project Manager
Jon March
Project Sponsor
Sheila Lodge
Current Stage
Close
Status
Withdrawn
Start Date
12-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Nov-2017
Overall Priority
Higher
Category
Compliance

Documentation

Close