Report for February 2019

Report Date
February 2019

Achievements

  • Recommendation approved by Project and key stakeholders
  • Delivery milestone complete and presented to IS WIS
  • Agreement to initiate a new project to manage the creation, testing and rollout of the recommendation

Issues

  • All closed

Next steps

  • Close report prepared, review, approve, submit to WIS and close project

Milestones

  • Closure milestone slightly delayed, will close in March 2019
Stage Milestone Due Date Previous Date Complete
Close Project Closure 15-Feb-2019 19-Oct-2018 No
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
130.0 days
Activity this month
1.0 day
Activity this year
21.9 days
Activity to date
21.9 days
Estimate to complete current year
50.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Reporting of assessment outcomes to external bodies
Code
MVM121
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Paul De'Ath
Project Sponsor
Nicola Crowley
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-May-2017
Planning Date
25-May-2018
Delivery Date
31-Jan-2019
Close Date
22-Mar-2019
Programme Priority
2
Overall Priority
Normal
Category
Discretionary