January 2018

Report Date
January 2018

Achievements

  • Meeting to review the Business Case Report and select the best option for Biomedical Sciences (BMS) to access Simitive WAM took place on the 9 January. Decision was taken to join the CAHSS installation if/when the HSS020 Project Board agree to roll-out to the rest of the CAHSS College.
  • Business Case (Delivery - Options review  milestone) was signed off on 9 January.
  • Agreement to extend the project to prepare for adopting WAM and joining the CAHSS installation. PMs for MVM124 and HSS020 have worked together on these preparations.
  • The HSS020 Project Board meeting was on the 25 January 2018 and agreed to deploy Simitive WAM for the College on an opt-in basis.

Issues

  • None

Next steps

  • Agree when BMS will join the CAHSS WAM deployment, how and the governance needed.
  • Incorporate BMS in the CAHSS WAM follow on project
  • Close Project

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
PICCL 1 (https://www.projects.ed.ac.uk/unpublished/project/mvm124/issues/1) that increases the budget and moves the project end date was not approved in time and need to be resubmitted.
Change Status
Activity
Approved budget
6.0 days
Activity this month
2.7 days
Activity this year
8.4 days
Activity to date
6.0 days
Estimate to complete current year
3.6 days
Estimate to complete future years
0.0 days

Project Info

Project
WAM pilot for Biomedical Sciences - options review
Code
MVM124
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Geoff Cropley
Project Sponsor
Sheila Lodge
Current Stage
Close
Status
Closed
Start Date
04-Dec-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
23-Mar-2018
Programme Priority
3
Overall Priority
Normal
Category
Discretionary