April 2021

Report Date
April 2021

Achievements this period

  • No progress due to delays from the associated sites noted in last month's report

Issues

  • None

Next Steps

  • Continue to deploy teaching tablets to relevant locations.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Connectivity - Off-campus
Code
MVM125
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
04-Feb-2019
Planning Date
n/a
Delivery Date
28-Oct-2021
Close Date
29-Oct-2021
Overall Priority
Normal