Overview

Background

Each year the College replaces the AV facilities in a number of teaching spaces across its estate.  We are trying to move to a 5 year replacement cycle, however this is dependant on available funding.  For financial year 2018/19 the replacements are below.

 

Scope

Complete AV upgrade of Kennedy Tower Division Lecture Theatre.

6 rooms in the Clinical Skills Centre within Chancellor's Building (including simulation manikins).

Rooms TBC in the Vet School.

Resolve 4K issue in Chancellor's Building Lecture Theatre A.

 

Objectives

To replace the AV installations in the above rooms within a timely manor and with the least amount of inconvenience to the users.

 

Deliverables

 

 

Benefits

 

 

Success Criteria

All rooms and equipment are upgraded and paid for within the financial year.

 

Project Milestones

(Please copy and paste from Milestones log)

Project Info

Project
Upgrading of teaching spaces 2018/19
Code
MVM130
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Sheila Fraser
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
15-Oct-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Nov-2019
Overall Priority
Normal
Category
Discretionary

Documentation

Plan