Closure Report

Project Summary

This project followed on from the successful conclusion of MVM121 (Reporting of assessment outcomes to external bodies) which delivered an approved recommendation paper identifying an option that all contributors approved.

MBChB currently run a series of manual activities across a number of spreadsheets to rank all MBChB students. Both timely and containing risk of human error, this project set out to create new BI-Suite reports which MBChB can execute whenever they need to. The intention was for them to be easy to use but containing options (adjust weightings, select years etc), fully supported and to be ready for summer 2019 use.

As is explained in more detail below, the project has delivered but it is almost a year later than planned.

Scope as defined in the Brief:
  • Create new object in the Universe
  • Create new reports that MBChB assessment team can execute independently within bi-suite - based on requirements generated in MVM121
  • Provision of super user training for MBChB assessment team
  • Develop and sign off User Acceptance Testing to validate the reports - functionally and technically
  • Support MBChB assessment team maintaining their manual spreadsheet execution of student ranking - will act as both data input and will also de-risk the project
  • Communication to all stakeholders
  • Create an agreed support model for the reports
  • Extend MBChB change - not just the technical elements surrounding the introduction of the new reports, but the structural, process and people based change that will emerge alongside the technical delivery

The scope of this project has been delivered however:

  • Due to Covid-19 and the changes made to how students had been/are being assessed, work was required to amend the report (this is noted in change control 8).
  • Minor enhancements to the report were also delivered during the training session with no additional time or effort required.

 

Objectives And Deliverables as defined in the Brief:

No.

Description

Priority     

Achieved?
O1  Deploy two new bi-suite reports for MBChB to execute student ranking.    

D1

 Create new object(s) in universe

  M

Yes

D2

 Manage creation of two reports utilising this object and matching MBChB requirements

  M

Yes
D4  Ensure MBChB staff attend and pass 'super user' training   M Yes
D5  Decommission manual spreadsheet work   M Yes
D6  Agree and create a new support model   M Yes

 

Ongoing support for report amendments has been agreed as being via standard mechanism of raising Unidesk calls to the Student Data and Reporting team. Within the MBChB programme, there is an agreed lead owner of the reports with support from another named colleague. Both these users have completed training in how to use the report. The project delivered one report and following the training, the business lead has been able to create two other reports..

 

 Benefits as defined in the Brief:
  • Improving assessment and feedback of the students is considered the number one priority for the Medical School. Student ranking is therefore seen as a critical element by many students. Currently it's an extremely timely process for MBChB to produce, with several iterations of build and check with several members of the team to try and reduce the potential of a human error occurring. These new reports will remove any potential for human errors to occur and will also allow MBChB to execute quickly

The benefits of this project have been delivered. This has improved efficiency for the team producing the report and removed the risk of human error, which will enable the ranking for the General Medical Council to be accurately achieved in a reduced timeframe in future.

 

Success Criteria as defined in the Brief:
  • Supporting the construction of student ranking during the summer 2019 and beyond with quality data and improved best practise.

The success criteria has been partially met: the student ranking with quality data and improved best practice was delivered. This was achieved after the summer of 2019; it was delayed in agreement with the business area due to their local priorities.

 

Analysis of Resource Usage:

Staff Usage Estimate: 42 days

Staff Usage Actual: 26 days (12 days in 18/19 and 14 days in 19/20)

Other Resource Estimate: N/A

Other Resource Actual: N/A

Other Resource Variance: N/A

 

Explanation for Variance

  • Although it would appear from the figures that this project has delivered under budget, this project has expended Project Management effort securing resources and maintaining the project record over a prolonged period.
  • The project has delivered almost a year late and this has been due to the reliance on a few key people in the University to be able to do the work. The Business Lead in MBChB is a critical resource for CMVM and is required for high priority business as usual work, alongside delivering project work. Securing time with the MBChB lead was the main challenge from November 2019 to March 2020. Initial delays were due to dependency on the  key Business Analyst resource in SSP.  Changes controls 3, 4, 5 and 6 all note the impact from these resource conflicts during this project.
  • The Covid-19 outbreak exacerbated the challenge with securing time with the MBChB lead  and re-work that was required due to the changes in how students were being assessed and therefore this has caused additional delay from April 2020 to delivery at the start of July 2020. Change control 8 reflects the delay impact due to Covid-19.

Outcome

This project has delivered a workable and sustainable solution in fewer days  effort than had originally been expected. This has been a successful partnership between the Business, SSP, and IS Application and has built on the worthwhile analysis that was completed in the previous project.

Key Learning Points

Ref Date Title Impact Theme Stage  
1 17-Jul-2020 Availability of critical business resources needs to be considered in initial planning; for example, during exam board time, these resources should not be considered available for project time Was detrimental Resourcing Accept

 view

2 17-Jul-2020 Decision grid for BI reports' location and access Was beneficial Management of a Project Design

 view

 

Outstanding Issues

None

Project Info

Project
MBChB ranking reports in BI Suite
Code
mvm132
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Nicola Crowley
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Apr-2019
Planning Date
26-Apr-2019
Delivery Date
03-Jul-2020
Close Date
31-Jul-2020
Overall Priority
Normal
Category
Discretionary

Documentation

Close