Report for May 2020
- Report Date
- May 2020
Achievements this period
- Reports altered to reflect impact from Covid-19 exams decisions.
- Milestones rescheduled to accommodate business lead's availability to test.
Issues
- None
Next Steps
- Complete testing
- Closure
Milestones
Stage | Milestone | Due Date | Previous Date | Complete |
---|---|---|---|---|
Deliver | Delivery of reports complete | 03-Jul-2020 | 03-Apr-2020 | No |
Close | Closure report complete and approved | 31-Jul-2020 | 30-Apr-2020 | No |
- Approved budget
- 42.0 days
- Activity this month
- 0.3 days
- Activity this year
- 10.4 days
- Activity to date
- 22.0 days
- Estimate to complete current year
- 6.0 days
- Estimate to complete future years
- 11.4 days