Report for May 2020

Report Date
May 2020

Achievements this period

  • Reports altered to reflect impact from Covid-19 exams decisions.
  • Milestones rescheduled to accommodate business lead's availability to test.

Issues

  • None

Next Steps

  • Complete testing
  • Closure

Milestones

Stage Milestone Due Date Previous Date Complete
Deliver Delivery of reports complete 03-Jul-2020 03-Apr-2020 No
Close Closure report complete and approved 31-Jul-2020 30-Apr-2020 No
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Significant
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
The delivery date has been revised by three months to accommodate the impact of Covid-19
Activity
Approved budget
42.0 days
Activity this month
0.3 days
Activity this year
10.4 days
Activity to date
22.0 days
Estimate to complete current year
6.0 days
Estimate to complete future years
11.4 days

Project Info

Project
MBChB ranking reports in BI Suite
Code
mvm132
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Nicola Crowley
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Apr-2019
Planning Date
26-Apr-2019
Delivery Date
03-Jul-2020
Close Date
31-Jul-2020
Overall Priority
Normal
Category
Discretionary

Documentation