Report for June 2020

Report Date
June 2020

Achievements this period

  • Testing of reports took place which identified a number of fixes that were required
  • Revised report provided to business lead for final testing
  • 2 requests for change have been agreed as out of scope for the project

Issues

  • None.

Next Steps

  • Complete testing and confirm delivery of reports
  • Close

Milestones

Stage Milestone Due Date Previous Date Complete
Deliver Delivery of reports complete 03-Jul-2020    03-Apr-2020 No
Close Closure report complete and approved               31-Jul-2020 30-Apr-2020 No

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
MBChB ranking reports in BI Suite
Code
mvm132
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Nicola Crowley
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Apr-2019
Planning Date
26-Apr-2019
Delivery Date
03-Jul-2020
Close Date
31-Jul-2020
Overall Priority
Normal
Category
Discretionary

Documentation