Report for January 2020

Report Date
January 2020

Achievements

  • Added a progress bar so students can see a completion percentage when completing an evaluation
  • Obfuscate the URLs for a report that is shared with a guest user
  • Allow users to download reports in PDF format

Issues

  • Tutor evaluations had not been implemented correctly. Additional tasks added to fix tutor evaluation implementation.
  • Two features identified that were missing in original system. Group bulk upload and evaluation search. Tasks added to implement these features

Next Steps

  • Fix tutor evaluation implementation
  • Add missing features to align with previous evaluation system
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Project is likely to delivery two months over initially agreed December date. The bulk of the work has been completed by two developers. One developer will remain on project to complete final tasks which we estimate will be completed by the 14th of February.
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
The project is now expected to deliver just over 2 calendar months after the agreed project deadline. This extension includes a break in development for the Christmas holidays.
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
MBChB Evaluation System
Code
MVM134
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Andrew Millington
Project Sponsor
Sheila Fraser
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
09-Sep-2019
Planning Date
09-Sep-2019
Delivery Date
06-Dec-2019
Close Date
08-Apr-2020
Overall Priority
Normal
Category
Discretionary