Overview

Background

Each year the College replaces the AV facilities in a number of teaching spaces across its estate.  We are trying to move to a 5 year replacement cycle, however this is dependant on available funding.  For financial year 2019/20 the replacements are below.

 

Scope

Vet School room G45 camera system - this is a requirement from last financial year.

Completion of Western General Hospital Medical Education Centre Simulation Suite.

Complete AV upgrade of Greenfield Suite Main Computer Lab.

Complete AV upgrade of side rooms 4 and 5 in the Greenfield Suite.

Complete AV upgrade of seminar rooms 1-4 in the Henry Littlejohn Suite.

Various rooms within the Veterinary School - numbers of rooms to be confirmed as funding allows.

 

Objectives

To replace the AV installations in the above rooms within a timely manor and with the least amount of inconvenience to the users.

 

Deliverables

 

Benefits

 

Success Criteria

All rooms and equipment are upgraded and paid for within the financial year.

 

Project Milestones

(Please copy and paste from Milestones log)

Project Info

Project
Upgrading of Teaching Spaces 2019/20
Code
MVM135
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Close
Status
Closed
Start Date
09-Dec-2019
Planning Date
n/a
Delivery Date
31-Jul-2020
Close Date
15-Oct-2020
Overall Priority
Normal

Documentation

Execute