Closure Report

Project Summary

Campus Room/Equipment Completed Notes
All Webcams and tabletop mics for online teaching No Webcam delivery has been delayed multiple times due to lack of stock in the UK (COVID-19 has been the cause of this)
All Keyboard Covers for presenter PCs (due to COVID-19) Yes  
WGH MEC Simulation Suite Yes  
WGH East Seminar Room E4.07 Yes  
Central Greenfield Suite Main Lab No All equipment has been delivered but installation hasn't taken place due to COVID-19 situation.  Installation will be carried out during financial year 20/21.
Central Greenfield Suite Side Rooms 4 & 5 No All equipment has been delivered but installation hasn't taken place due to COVID-19 situation.  Installation will be carried out during financial year 20/21.
Central  Henry LittleJohn Suite (4 Rooms) No All equipment has been delivered but installation hasn't taken place due to COVID-19 situation.  Installation will be carried out during financial year 20/21.
Central Dermatology Seminar Room Yes  
Central MacKenzie Medical Practice Room 1.03 Yes  
Central Sydney Smith LT (Catchbox) Yes  
Easter Bush Vet School G.45 Camera and Mount No All equipment was delivered and initially installed, however there were issues with the mount which then needed to be sent back to the manufacturer for modifications.  The new installation will be scheduled with the Vet School staff.
Easter Bush Vet School rooms 1.42 - 1.46 No All equipment has been delivered but installation hasn't taken place due to COVID-19 situation.  Installation will be carried out during financial year 20/21.
Easter Bush Teaching Lab 1 No All equipment has been delivered but installation hasn't taken place due to COVID-19 situation.  Installation will be carried out during financial year 20/21.
Easter Bush Clinical Skills 1.21 No All equipment has been delivered but installation hasn't taken place due to COVID-19 situation.  Installation will be carried out during financial year 20/21.
Easter Bush F Block Clinical Skills No All equipment has been delivered but installation hasn't taken place due to COVID-19 situation.  Installation will be carried out during financial year 20/21.
BioQuarter Chancellor's Building FU305 No All equipment has been delivered but installation hasn't taken place due to COVID-19 situation.  Installation will be carried out during financial year 20/21.
BioQuarter SCRM Large Seminar Room 1.32 (lecture recording) No All equipment has been delivered but installation hasn't taken place due to COVID-19 situation and additional AV upgrades being required (at SCRM cost).  Lecture recording installation will be carried out when the additional AV upgrades are funded and scheduled in.

 

 

 

 

Outcome

Due to the COVID-19 situation, it was not possible to install all of the AV upgrades as part of this project, however all of the necessary equipment was procured last financial year, as well as some additional equipment to assist with the new remote teaching requirement.  The installation of the remaining AV upgrades will be funded from the financial year 20/21 budget and relevant details will be incorporated into the new project (MVM143).

There was a substantial amount of funds left in the associated budget for this project, which we couldn't make use of, as the MVM Learning and Teaching IT Lead was only made aware of this underspend close to the end of the financial year and IS didn't want to risk the possibility of not being able to goods receipt equipment before the end of the financial year.  If the underspend was known about sooner, additional equipment could have been purchased to upgrade other teaching rooms across MVM.

Project Info

Project
Upgrading of Teaching Spaces 2019/20
Code
MVM135
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Close
Status
Closed
Start Date
09-Dec-2019
Planning Date
n/a
Delivery Date
31-Jul-2020
Close Date
15-Oct-2020