August 2020

Report Date
August 2020

Achievements this period 

  • AV installation in Mackenzie Medical Practice room 1.03 took place on 4th August.
  • AV installation in Dermatology seminar room took place on 5th August.
  • Various pieces of equipment for the Greenfield Suite main lab, side rooms and Henry Littlejohn rooms have started to be delivered. 

Issues

  • The camera mount installed in Vet School G.45 on 3rd August hadn't been fully customised to our requirements, so has had to be sent back to the manufacturer to be adjusted.  A timeframe for the adjustments hasn't been provided yet.
  • We are still waiting for the webcams and other minor AV parts to be delivered.

Next Steps

  • Remaining rooms for upgrading will be scheduled as and when the AV kit, AV contractors and estates work are ready.
  • Further investigation regarding the equipment requirements for Vet School 1.21 Clinical Skills needs to be carried out.  This will need to wait until the building is reopened, as testing of the existing equipment is required.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Remaining at AMBER as we're still waiting for several deliveries and don't currently have a time frame for when the Greenfield Suite and Henry Littlejohn rooms will be able to be upgraded.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Upgrading of Teaching Spaces 2019/20
Code
MVM135
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Close
Status
Closed
Start Date
09-Dec-2019
Planning Date
n/a
Delivery Date
31-Jul-2020
Close Date
15-Oct-2020
Overall Priority
Normal

Documentation