Report for September 2020

Report Date
September 2020

Of the 26 rooms that were scheduled to be upgraded during financial year 19/20, only 8 have been completed in full.  The AV equipment relating to the remaining 18 rooms has been delivered to the University, however due to the COVID-19 situation, the installations haven't been possible yet.  These installations will be funded and carried out in financial year 20/21 using any central AV budget that we receive.  Any remaining funds from the budget we receive for financial year 20/21 will then be used to upgrade the next round of MVM teaching spaces. 

 

The closure report for this project can be found here

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Upgrading of Teaching Spaces 2019/20
Code
MVM135
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Close
Status
Closed
Start Date
09-Dec-2019
Planning Date
n/a
Delivery Date
31-Jul-2020
Close Date
15-Oct-2020
Overall Priority
Normal

Documentation