Report for April 2021
- Report Date
- April 2021
Achievements this period
- Issue with period 5 payment resolved
- Vets, BMTO, Admissions provided with discounted rates for 20/21
- Some progress was made on the Vets' OSCES marking
- Project closure report drafting underway
Issues
- Vets required revised milestones to complete marking and confirm delivery - resolved
Next Steps
- Marking in Practique of Vets OSCEs to complete in start of May - this is final delivery
- Complete project closure
Milestones
Milestone | Due Date |
Delivery of all Practique elements | 07-May-2021 |
Project Closure approved | 21-May-2021 |
- Approved budget
- 40.0 days
- Activity this month
- 0.7 days
- Activity this year
- 9.2 days
- Activity to date
- 31.4 days
- Estimate to complete current year
- 3.0 days
- Estimate to complete future years
- 0.0 days