Report for April 2021

Report Date
April 2021

Achievements this period

  • Issue with period 5 payment resolved
  • Vets, BMTO, Admissions provided with discounted rates for 20/21
  • Some progress was made on the Vets' OSCES marking
  • Project closure report drafting underway

Issues

Next Steps

  • Marking in Practique of Vets OSCEs to complete in start of May - this is final delivery
  • Complete project closure

Milestones

Milestone Due Date
Delivery of all Practique elements 07-May-2021
Project Closure approved 21-May-2021

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
40.0 days
Activity this month
0.7 days
Activity this year
9.2 days
Activity to date
31.4 days
Estimate to complete current year
3.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Practique Roll-Out
Code
MVM136
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Sep-2019
Planning Date
10-Oct-2019
Delivery Date
07-May-2021
Close Date
21-May-2021
Overall Priority
Normal
Category
Discretionary

Documentation