Report for January 2020

Report Date
January 2020

Achievements

  • Framework structure is in place. Laravel for the backend, and VueJS for the front end. The two systems can communicate with one another successfully
  • Added ability to view list veterinary practices types
  • Added ability to add veterinary practice types

Issues

  • We had planned for two developers to work on this project in conjunction, but only have one available at present due to MVM134 overrunning.

Next Steps

  • Continue to build functionality to manage veterinary practices in the system
  • Add second developer to project workload
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Time is amber due to reduced number of developers working on the project at present.
Change Status
Has formal escalation taken place?
No
Change Commentary
No change as first reporting month
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Vets EMS Placement Management
Code
MVM138
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Andrew Millington
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
20-Jan-2020
Planning Date
n/a
Delivery Date
31-Aug-2020
Close Date
05-Sep-2020
Overall Priority
Normal
Category
Discretionary

Documentation