Report for June 2020

Report Date
June 2020

Achievements

  • Integrate feed of students from Euclid with the system
  • Add reports
  • Add student photographs to system

Issues

  • None

Next Steps

  • Allow vets to access placement information
  • Handover to vet school for testing and deployment
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Development is expected to complete mid July. This is later than expected but within project tolerances.
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
Time has been lost due to staff leave associated with the Covid-19 pandemic. The project will deliver later than expected but within project tolerances
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Vets EMS Placement Management
Code
MVM138
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Andrew Millington
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
20-Jan-2020
Planning Date
n/a
Delivery Date
31-Aug-2020
Close Date
05-Sep-2020
Overall Priority
Normal
Category
Discretionary

Documentation