Report for August 2020

Report Date
August 2020

Achievements

  • Set up project for next development phase
  • Removed sections from the site that are not used/no longer required

Issues

  • Just one developer working on the system at present. More developers will be added to this project in early September

Next Steps

  • Begin work on the curriculum approval process
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Starting this project later in the year than anticipated so have flagged time as amber.
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
Starting project later than projected.
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Curriculum Mapping Tool (COMMAND)
Code
MVM139
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Andrew Millington
Project Sponsor
Susan Rhind
Current Stage
Execute
Status
Closed
Project Classification
Grow
Start Date
20-Jan-2020
Planning Date
n/a
Delivery Date
26-Feb-2021
Close Date
02-Apr-2021
Overall Priority
Normal
Category
Discretionary

Documentation